CCMUA is seeking services of a qualified and experienced consulting firm to obtain engineering design services to upgrade and replace the Camden County Municipal Utility Authorities existing WRRF’s 26.4-4.16KV main substation. The project includes the upgrade and replacement of the existing main plant substation. The replacement substation will be located directly next to the existing substation, in the area presently used for construction trailers and staging areas and built while the existing substation is still in service. The replacement substation will be air conditioned and elevated above the required resiliency flood elevation to house the new switchgear cabinets, generator PLC panel, batteries, and all other required electrical equipment and shall be constructed with the existing substation still in service. The proposal shall also include the extension of the existing roads and curbing to the new elevated building, complete with an area designated for parking, as shown on the 30% design plans.