The construction project involves building a 9,209 sq. ft. gymnasium addition. Contractors may submit proposals for the entire project or for individual tasks, as outlined below: A. Site Preparation and Demolition 1. Demolition and Clearing: - Removal of existing structures, utilities, pavements, and fencing per the Demolition Plan. 2. Erosion and Sedimentation Control: - Installation of silt fencing, mud tracking mats, and inlet filters before any grading or construction begins. - Maintenance of erosion controls throughout construction. 3. Grading and Earthwork: - Grading the site to achieve a finish floor elevation of 149.00 ± per the Grading Plan. 4. Utility Cut, Cap, and Relocation: - Disconnecting, capping, and relocating utilities, including gas, water, and electrical connections. B. Foundation and Structural Work 1. Foundations: - Installation of reinforced concrete foundations and frost slabs. 2. Structural Framing: - Erection of structural steel framing for roof and wall support. 3. Masonry Walls: - Installation of load-bearing CMU walls with brick veneer and split-face block accents. 4. Roofing System: - Installation of insulated low-slope roofing with rooftop HVAC equipment screening. C. Building Exterior 1. Facade Construction: - Aluminum-framed clear-story windows and decorative metal canopies above entrances. 2. Entrances and Doors: - Hollow metal insulated doors for exterior access points. D. Interior Build-Out 1. Gymnasium Flooring: - Installation of maple wood flooring with subfloor preparation and expansion voids. 2. Locker Rooms and Bathrooms: - ADA-compliant locker rooms and bathrooms with hot and cold-water systems. 3. Concession Area: - Construction of countertops, food service shelving, and sink installations. 4. Storage and Mechanical Rooms: - Heavy-duty shelving and fire sprinkler systems. E. Mechanical, Electrical, and Plumbing (MEP) Systems 1. HVAC Systems: - High-efficiency rooftop HVAC units (15-ton and 7.5-ton capacities). 2. Plumbing Systems: - Installation of sanitary and stormwater systems. 3. Electrical Systems: - Power distribution, lighting, and emergency exit signage. F. Exterior Site Work 1. Parking and Landscaping: - Construction of 43 parking spaces and ADA-compliant walkways. 2. Fencing and Gates: - Erection of a 6-foot-high metal fence with sliding gates. G. Gymnasium-Specific Features 1. Sports Equipment: - Retractable basketball hoops and motorized bleachers. 2. Acoustic Treatments: - Sound-absorbing wall panels to minimize noise. 3. Audio-Visual Systems: - Installation of a public address system.