Task 1: Kick off meeting and permitting; Task 2: Health and Safety Plan; Task 3 : Permitting; Task 4: Mobilization and Demobilization; Note: Tasks 5 – 11 shall include: All of the labor and materials as necessary to complete each of the described and detailed tasks; Task 5: remove and legal dispose of the Phase 1 and Phase 2 concrete plaza located at the rear of City Hall; Task 6A: construct the poured in place concrete planters as shown with the approved wall form-liner, as specified and detailed on the project documents and per the manufacturer’s instruction; Add-Alternate Task 6B: construct the poured in place concrete planters as shown with the approved limestone slab and approved stainless steel anchors, as specified and detailed on the project documents; Task 7: reconstruct the concrete plaza as shown, specified and detailed on the project documents; Task 8: provide and install all of the topsoil for the planters as shown, specified and detailed on the project documents; Task 9: provide and install 18 of the specified 2” -2.5” cal. Shade Trees as shown, specified and detailed on the project documents; Task 10: provide and install all of the ground cover and mulch within the planters as shown, specified and detailed on the project documents...