Scope of Work: The following activities are included in this project’s scope of work: • Survey and flag/mark an approximate 5- to 7-mile sustainable multi-use trail route from Skagway Rifle Range to approximately the Dyea raft pullout area, with a spur dropping into the municipally owned Nahku Bay Conservation Area. • Develop trail design and construction narrative to include: o Trail map with GPS waypoints. o Recommended construction techniques to be used between waypoints. o Estimated trail construction schedule with phasing options. o Estimated construction cost to complete trail. o Estimated construction cost per phase. o Construction costs shall be developed using a schedule of values. The schedule of values will include pay item descriptions, pay units, approximate quantities, unit prices, and amounts. o Recommended locations for outhouses. o Recommended signage, viewpoints, trail markers, and their respective locations. o Final Recommendation for project. o Narrative completion by October 31, 2025.