1 Demolition of (E) Timber Fender Piles at East Berth 23 EA $ _______________ 2 Demo (E) Timber Fendering System at East Berth 575 LF $ _______________ 3 Demo (E) Bull Rail at Battery Locations at East Berth 330 LF $ _______________ 4 Demo and Salvage Temporary Fender System at East Berth 5 EA $ _______________ 5 Demo and Salvage of (E) Miscellaneous hardware and abandoned utilities at East Berth. 1 LS $ _______________ 6 Form and Place (N) Concrete Pedestal at East Berth 15 EA $ _______________ 7 Procurement and Install (N) Fenders and Associated 15 EA $ _______________ Hardware at East Berth 8 Procurement and Installation (N) 225MT Mooring Bollards at East Berth 8 EA $ _______________ 9 Mobilization (Maximum 10% of the sum of Bid Items 1 through 8) 1 LS N/A $ _______________ 10 Repair of Existing Bollards and areas around Fender Reaction Installations 1 AL $100,000 $100,000 11 Partnering 1 AL $ 20,000 $ 20,000