Madison Water Utility (MWU, Owner) is requesting cost proposals to furnish and install replacement components for the Unit Well 31 deep well, as well as a new LAKOS Pump Protection Separator capable of pumping at least 2,200 gallons per minute. MWU may also request the removal (by bailing) of all sand, stones or other foreign material deposited in the well in order to achieve a well depth of approximately 910 feet. Sequence of activities: 1) Mobilize and start work within 5 working days of receipt of the approved purchase order. 2) Coordinate setup, schedule, and operations with MWU. 3) Bail accumulated fill from the hole if requested by MWU. 4) Video survey the well to document pre-startup conditions (if bailing occurs). 5) Install deep well equipment and pump/motor in order to achieve pump startup. Materials not listed for bid in this document will be furnished by MWU. 6) Demobilize and clean up the site.