The existing transmission line structures, foundations, conductors, guys and anchors will be retired, and the new structures, pile foundations, and conductor installed. Existing and new 138kV conductors are 795 kcmil, ACSR “Drake”. This project involves: A. Retiring existing 138kV Structures ITRR 1-1, ITRR 1-2, and 1-2 and installing new 138kV Structures ITRR 1-1 and ITRR 1-2. Relocate 138kV conductors between existing ITSS A-frame structure and existing Structure ITRR 1-3. B. Retiring existing Structures ITUV 1-1, ITUV 1-2, and 100-07 and installing new Structures ITPM2 1-1/ITUV 1-1 (double circuit pole) and 100-07. Relocate 138kV conductors between existing ITSS A-frame structure and existing Structure 100-07. C. Retiring existing Structure ITPM2 1-1. Relocate 138kV conductors between existing ITSS A-frame structure and existing Structure 1-1 (0305)...