The Contractor will be responsible for electrical and plumbing connections to the lift tank. The Contractor will be responsible for the ditch and conduit to the Oncor transformer located approximately 30 feet to the west of the building. The Contractor will be responsible for securing the construction site from public access and maintaining pedestrian access to the sidewalk and walkways or designating an alternative pathway approved by the City of Early. SEQUENCE OF WORK 1. Pre-Construction Conduct site survey and soil testing. Provide adequate barriers to establish construction area. 2. Site Preparation 3. Foundation & Utilities 4. Building Construction 5. Interior Work 6. Final Site Work 7. Testing & Inspections Ensure ADA compliance and accessibility features. Address final punch list items and make necessary corrections. 8. Closeout & Turnover Perform the final cleaning of the facility. Conduct a final walkthrough with City Officials. Provide operation manuals, warranties, and as-built documentation.