The Project includes the following Work: roadway and utility reconstruction of Hamburg St from W Oshkosh St to the south approximately 1,600’ and Hennie St from Hamburg St to Pacific St. Utility Construction: approximately 2,200’ of PVC water main (6” –8”) including valves, hydrants, appurtenances and services; approximately 600’ of PVC sanitary sewer (8”) including manholes and laterals; approximately 1,900’ of storm sewer, RCP and HDPE (12”–30”) including manholes, inlets, and endwalls. Roadway Construction: approximately 2,000’ of roadway excavation and grading, geotextile fabric, breaker run, dense graded base, hot mix asphalt, concrete, gravel, and asphalt driveway replacement, concrete sidewalk and concrete curb & gutter. Tree removal, clearing, grubbing, site restoration, traffic control and erosion control are included in the project.