Furnish all steel lintels as shown. 4. Demolition of Existing Deck and Joist as shown for new mechanical equipment. 5. Furnish and Install Structural Steel Framing and reinforcement as shown. 6. Furnish and Install Steel Joist Framing as shown. 7. Furnish and Install Steel Decking as shown. 8. All onsite welding must be done by certified welders. 9. Provide Fire Watch for work completed above. 10. Dust control measures for all work in this Bid Category. 11. Daily clean-up at work areas. 12. Contractor to meet Project Schedule, this includes weekend work or daily overtime. a. Project Manager/Project Foreman required to attend the following meetings: i. Pre-Construction Kick Off ii. Bi-Weekly Progress Meeting iii. Any meetings required by the Local Ordinance, Architect, and/ or Civil Engineer 13. All work must be done in accordance with MIOSHA Regulations. a. Provide lifting plan for any crane work.