The project includes the following: a. Pump out existing Clivus Multrum® composting restroom and move to location within the park specified by the Park Facility Manager. b. Procure appropriate permit from the St. Mary’s County Health Department for installation of the proposed double vault restrooms. c. Excavate the site in accordance with the manufacturer’s specifications for installation of a CXT® Double Cascadian Vault Restroom with Chase, or acceptable alternative. d. Install 8” of specified aggregate bedding material under vaults, compacted in 4” lifts, using Unit Price #1. e. Coordinate with the Manufacturer on the installation of the CTX Double Cascadian Vault Restrooms with Chase including the requirements for proper backfilling, compacting, and finish grading. i. Note that the Manufacturer will prime and paint the interior and exterior of new restrooms at the factory. Provide the Manufacturer with draw down samples described below. ii. Note that the Manufacturer will install all door hardware, signage, and accessories such as the solar light and solar fan kits. f. Install Owner-furnished vandal-resistant soap dispenser in each restroom. g. Install an approximately 40’ long by 5’ wide, compacted gravel path from existing path along the east side of parking area to the front of installed unit, using Unit Price #1. h. Install 4” of screened topsoil, grading 15’ in all directions from unit following natural contours with an appropriate slope for rainwater to drain off the roof and away from the unit. Provide biodegradable ground matting and seed and straw over graded area. i. Remove and properly dispose of all excess dirt, material, and debris.