The Project consists of one prime Contract and includes but is not limited to the following approximate major Work items: 7,500 CY Common Excavation (Estimated) \ 100 CY Bed Rock Excavation (Estimated) \ 5,800 Ton Hot Mix Asphalt Pavement \ 9,700 Ton Dense Graded Base Course (1-1/4” and 3”) \ 3,000 LF 18”-30” Concrete Curb and Gutter Remove and Replace \ 6,700 SF 5” Concrete Sidewalk Remove and Replace \ 48 VF Sanitary Sewer Manhole \ 14 EA Existing Sanitary Manhole Chimney Repair \ 765 LF 8” Sanitary Sewer \ 2,270 LF 8” Watermain \ 7 EA 8” Gate Valve \ 5 EA Hydrant Assemblies \ 1,250 LF 1” Water Service \ 1,180 LF 6” Sanitary Lateral \ 775 LF 12” RCP Storm Sewer Pipe with Granular Backfill \ 12 EA 48” Storm Manhole with Casting \ 20 EA 24” x 36” Catch Basin with Casting \ 1 LS Dust Control \ 3,500 SY Lawn Restoration