Work includes the procurement and installation of five 10” plug valves and six 16” plug valves, along with the necessary fittings to ensure proper installation. The Area 5 WWTP, located at 506 106th Street Gulfside receives a point of connection prior to the transmission line continues eastward up to the west side of the Vaca Cut Bridge in Marathon located at approximately 117th Street Gulfside where the transmission main will be capped off for continuation towards the Area 6 Wastewater Treatment Facility in the near future under a separate Contract. Installation of the piping via directional drill method is selected due to the large number of existing utilities both overhead and underground in the City of Marathon and the Florida Department of Transportation (FDOT) right-of-way areas.