1. Environmental Pollution Control 1 LS LS $ 2. Traffic Control, including all labor, materials and equipment, in place, complete. 1 LS LS $ 3. Clearing, including disposal of debris. 1 LS LS $ 4. Rock Slope Scaling, including disposal of debris, all labor and equipment. 1 LS LS $ 5. Shotcrete Anchors, including all labor and materials, installed complete. 2,050 LF $ $ 6. Shotcrete, including trenching, reinforcing, keys, FRP dowels, rebar dowels, PJF, geocomposite drain mat, pre and during construction strength testing, all labor, materials and equipment, in place complete. 390 CY $ $ 7. Sculpted Shotcrete Finish, including all labor, materials, test panels, color stain, and equipment, in place complete. 1 LS LS $ 8. Temporary Rockfall Protection Fence 1 LS LS $ 9. As-Built Drawings 1 LS LS $ 10. Mobilization (Not to Exceed 6% of the Total Sum of All Items, Excluding the Bid Price for Items No. 10 through 14, Force Account and Allowance Items) 1 LS LS $