1. Verification of soil bearing capacities and compaction per the requirements and specifications. 2. Preparation of concrete test cylinders for curbs and sidewalks, per the requirements of the specifications. 3. Inspection of proof rolling of subgrade in proposed pavement areas prior to placement of base material. 4. Adequate compaction testing of fill aggregate base (and sufficient proctors and field cones accordingly) to ensure that compaction requirements are met on the job in general. 2/12/2025, 2 PM Page 2 of 3 5. Trench compaction testing every 50 lf of trench in proposed pavement areas, eight (8) inch maximum each lift. Trench compaction testing should also be performed in proposed lawn areas sufficient to ensure that specified compaction is being achieved. Testing in lawn areas should be at 50 lf intervals every other lift...