Specific Notes/Scope: The following is to be used for clarification of the intent of this work category. This is not a comprehensive list of scope items and work category will be responsible to provide all work for the sections listed above. 1. Provide layout and staking by licensed surveyor. Coordinate staking with CM/other trades. 2. Furnish and install all barricades and traffic control devices required for the scope of this WC. 3. Coordinate removals with CM/other trades. 4. Perform all sawcutting, removal, and off‐site disposal of all asphalt paving. 5. Remove and replace unsuitable subbase materials as determined in field, limits of removal and replacement to paid for under Allowance. 6. Haul all spoils off site. 7. Adjust storm structures. 8. Remove and replace catch basin casting and reseal structure. 9. Furnish, install, and compact all subbase materials. +/‐ .10’ 10. Prep subbase for all paving. 11. Restoration to be determined at time of completion, cost to be taken from Allowance.