In general and pursuant to Minnesota Statutes, the work consists of the construction of outlet stabilization, repairs and replacements, and pond dredging with approximately the following quantities: 4 LS Mobilization 39 EA Tree Removal 0.70 AC Clearing and Grubbing 2 EA Remove Reinforced Concrete Flared End Section (RC FES) 3 EA Remove Headwall Dissipator 27 LF Remove Reinforced Concrete Pipe (RCP) 1088 CY Muck Excavation - Offsite (EV) (Contaminated) 5 EA Reinforced Concrete Flared End Section (RC FES) 28 LF Reinforced Concrete Pipe (RCP) 10 EA Repair Storm Structure 3 EA Repair Storm Sewer 1 EA Storm Skimmer Structure 263 CY Random Riprap 17 EA 3-4’ Diameter Boulders 4 LS Dewatering Together with Miscellaneous Erosion Control, Downed Tree Removal, Salvaging and Reinstalling Mailboxes and Landscaping, Connecting Pipe to Storm Structures, Traffic Control, and Site Restoration.