Dredging: • Three (3) channels including a police boat slip (95’ x 474’ approximately 4’ deep cut and 871’ longest haul distance to shore unloading area), turn around for police boat slip (76’ x 64’ approximately 4.5’ deep cut and 676’ longest haul distance to shore unloading area), and main channel for boat landing ramps (365’ x 886’ approximately 3.5’ – 2’ deep cut and 982’ longest haul distance to shore unloading area). • The current elevations of the project area ranges between approximately 75’ MSL along the banks to 61’ MSL near the entrance to the project area from Lake Moultrie. Most of the project area is at an elevation of 68 to 69’ MSL. • The designed dredge depth is to an elevation of 65.0’ MSL with a 3:1 side slope. Estimated dredge volume to reach design depth is 43,500 cubic yards. Concrete: • Boat Ramps - Prep and install six (6) lane, 15’ x 109’ each, ramp totaling 12,242 square feet (see plan set for details) - Prep and install four (4) concrete abutment for dock gangway anchorage 33’ x 8’ (see plan set for foundation details)