A. Furnish all labor, equipment, materials, and other supplies and services necessary to 1. Construct the following structures with concrete blocks: a. Ten (10) dugouts, open to field side (24’ L x 14’ W x 12‘ H) b. One (1) Wall of Champions wall (80’ L x 6’ H) 2. Construct and install the following concrete pads: a. Ten (10) 336 SF concrete dugout pads (24’ L x 14’ W x 5” D) b. Eight (8) 285 SF concrete bleacher pads (20’ L x 16’ W x 5” D) c. One (1) 420 SF concrete ‘Wall of Champions’ wall pad (84’ L x 6’ W x 5” D) d. One (1) 3,500 SF concrete batting cage pad (70’ L x 50’ W x 4” D) 3. Construct & Install five (5) 12” wide and 12” deep 3,000 psi concrete backstop wall footings from dugout to dugout at each field (890 LF total), to include 8-inch 30-foot square tubing poles (890 LF, 32.97 CY) 4. Install 590 LF of Nylon 1 ¾" square knotted 16-gauge twin inline backstop netting system at all fields to extend from each dugout, anchored from the top of a 3' backstop block wall precast cap and extend up to 24' in height (14,160 SF total). 5. Construct & Install 890 LF of 3-foot high backstop walls at five (5) fields using 8" X 8" X 16" split face block in running bond with 4" thick X 10" wide X 4' length precast wall coping cap from dugout to dugout and vertical #4 rebar dials 36" on center. a. Field #1: 168 LF b. Field #2: 172 LF c. Field 3: 204 LF d. Field 4: 170 LF e. Field 5: 176 LF 6. Install 3,500 SF of batting cage turf in the batting cage area (50’ x 70’).