1. Clean brick and structure (no high pressure washing on brick or masonry surfaces). Use non‐ionic detergent and water with medium bristle brush to clean brick and masonry. 2. Seal brick and masonry with Sikaguard 277 Enviroseal or Sika Masterprotect H177. 3. Clean wood surfaces with same cleaner as used on the brick. Pressure washing is allowed on wood surfaces. 4. After cleaning all exterior wood surfaces, replace any and all damaged or decayed wood material with like materials and like design, tighten any loose nails, screws etc. 5. All exterior wood surfaces, remove all loose or flaking paint, caulk tight, and seal gaps and holes of all unnecessary openings. Apply two coats Sherwin‐ Williams Woodscapes Exterior acrylic solid color house stain. Color to match existing. 6. Interior masonry or stucco, two coats Sherwin‐Williams Super Paint Exterior acrylic latex paint of same color as exterior wood surfaces. 7. Remove all roof coverings to reveal roof sheathing and inspect for damaged or decayed sheathing. Replace with fire retardant treated plywood any roof sheathing deemed necessary. 8. Inspect skylight, replace if required with similar type and size (see alternate 1). 9. Cover roof sheathing with ice and rain shield. Flash junction of roof sheathing and siding and skylight as necessary to maintain watertight junction. 10. Cover roof with Certainteed Highland Slate, black granite color, and install new metal drip edge color to match siding color. 11. Replace screen wire on interior of louvers with aluminum screen wire. 12. Contractor will clean site, haul off, and dispose all debris at the end of each workday. 13. Contractor will install safety fencing and or barricades around project site. 14. Contractor will protect clock tower mechanisms from any damage caused by this renovation project. 15. Contractor will protect all vegetation, live or artificial, from damage by renovation process. 16. Contractor to provide all necessary labor, materials, tools, safety equipment, scaffolds and or personnel lifts etc., for completion of this project. 17. Project to be complete within sixty (60) days of award of contract. Any extension of this time is at the discretion of the owner. ALTERNATE 1: Remove existing skylight and flashing and replace with like type and size skylight and replace existing flashing with similar material.