The work to be performed and provided under this Contract shall consist of furnishing all labor, materials, tools, equipment, safety equipment, permitting, erosion and sedimentation control measures, taxes, profit, overhead, testing, startup, and other costs and effort required to complete the following: Removal of approximately 108 linear feet of CMP and replacement with RCP, Installation of approximately 303 linear feet of 8” DIP gravity sewer, Installation of approximately 1,545 linear feet of slip lining existing sewer, Installation of approximately 940 linear feet of 6” DIP water main, Installation of approximately 1,705 linear feet of 8” DIP water main, Installation of approximately 500 linear feet of 10” DIP water main, Installation of approximately 4,672 linear feet of 2” PE gas main, Installation of approximately 547 linear feet of 3/4" PE gas main, Installation of approximately 4,430 linear feet of power/telecommunications ductbank, Removal and replacement of asphalt and striping