The Contractor’s Work shall include the following services: 2.1.1 Connect 230 kV and 35 kV power transformer leads. Install and terminate control wiring for power transformer. Transformer manufacturer will install and setup transformer on concrete pad. 2.1.2 Install three 35 kV breakers. Installation includes assembly, power leads, grounding and control wiring. Contractor may be responsible for transporting the equipment to the site from the Town’s warehouse or existing station yard. 2.1.3 Install one 230 kV breaker. Installation includes assembly, power leads, grounding and control wiring. Contractor may be responsible for transporting the equipment to the site from the Town’s warehouse or existing station yard. 2.1.4 Assemble and erect all steel structures including columns, beams, pedestals, trusses, steel poles and miscellaneous components necessary to construct a complete station structure in accordance with shop drawings and general arrangement drawings. Includes work in existing station 2.1.5 Install two 35 kV vacuum reclosers in accordance with the manufacturer’s instructions. Contractor may be responsible for transporting the equipment to the site from the Town’s warehouse. Installation includes assembly (if necessary), power leads, grounding, AC and control wiring. Contractor shall make-up power leads for all future reclosers. Contractor may be responsible for transporting the equipment to the site from the Town’s warehouse or existing station yard...