Specifications include, but are not limited to: The work comprises, but is not limited to: mobilization; traffic control; construction of ~6,100 LF of PVC recycled water main; construction of water services (include tie-in of existing water meters to recycled water systems); installation of new valves, blow-off assemblies; air-vac assemblies; end-cap fittings; and connection to an existing 30-inch CML&C steel water main owned by IEUA. The work also includes 1.5-inch full-width grind and AC overlay; adjustment of utility covers to grade; and restoration of striping, pavement markings/ markers, and legends. The work finally includes construction of a HAWK signal (pedestrian crossing signal) at Eucalyptus Avenue and Galloping Hills Road. The limits of the work are shown in the maps on sheets 1 and 3 of the Project Plans, and include Eucalyptus Avenue, Chino Hills Parkway, Avenida De La Flores, and Galloping Hills Road.