Specifications include, but are not limited to: a) Contractor will: i) Provide bridge cost estimates and associated limited schedule during preliminary and final design phases, using contractor style (production-based) methodologies and production-based heavy civil estimating software platforms. Cost estimates and the associated schedule are expected to occur at various stages during the design phase (assume 3 estimates/schedules at 30% (signing of Bridge Rehabilitation (07042)/Repair (52009) Recommendations), 95% (Civil Rights Goal Setting estimates) and 100% (EE’s)) project milestones. ii) Provide intermediate bridge aesthetic cost estimates as design progresses (approximately 40-60% design stage to assist State in setting project budget and aid in local government participation negotiations. iii) Provide intermediate bridge utility cost estimates as design progresses (approximately 40-60% design stage to assist State in setting project budget and aid in local government participation negotiations. b) Preliminary 30% Estimates and schedule i) Contractor will be responsible for developing anticipated pay items and estimated quantities along with pricing developed items based on signed Bridge Rehabilitation (07042)/Repair (52009) Recommendation...