Specifications include, but are not limited to: The Project contemplated consists of the construction of one bifurcated cast-in-place concrete tank and performing related required work. The project includes the following major components as identified on the Bid Form: 1. Mobilization and Demobilization to the site, including all temporary construction facilities 2. Trenching, sheeting, shoring, and bracing as required by Section 6707 of the California Labor Code 3. Water Pollution Control Plan 4. Tie-Back Soil Anchor Design 5. Demolition 6. Civil Site Work and Grading 7. Phase 1 Tank 2 Construction 8. Phase 2 Tank 1 Construction 9. Retaining Wall Construction (walls not associated with Tank structures) 10. Existing Slab Repair 11. Yard Piping 12.Site Finishing (including gravel surfacing, sidewalk and driveway concrete, asphalt and road repair within the limits of the WTP) 13. Electrical and Instrumentation installation 14.SCADA Integration 15.All remaining work