Specifications include, but are not limited to: HOUSTON STREET WIDENING FROM GARNETT ROAD TO OLIVE AVENUE: This project includes roadway improvements including milling and overlaying existing Asphalt and adding new asphalt for widening on Houston Street from Garnett Road to Olive Avenue. The pavement configuration will include two through lanes in each direction and a center turn lane. The project includes 9,700 CY of Unclassified Excavation; 2,200 CY of Unclassified Borrow; 2,500 LF of Temporary Silt Fence; 28,000 SY of Solid Slab Sodding; 18,500 SY of Subgrade Method B; 19,600 SY of Separator Fabric; 25,000 SY of Fabric Reinforcement w/ Bituminous Binder; 5,850 Tons of Superpave, Type S3; 4,100 Tons of Superpave, Type S4; 20,900 SY of Cold Milling Pavement; 2,200 SY of Dowel Jointed PC Concrete; 5,805 lbs. of Reinforcing Steel; 11,500 LF of 2’-2” Combined Curb and Gutter; 6,750 SY of 4” Concrete Sidewalk; 1,750 SY of 8” Concrete Driveway; 1,630 LF of 24” Corrugated Polyethylene Pipe; 3,500 SY of Removal of Asphalt Pavement; 2,360 SY of Removal of Sidewalk; 1,880 SY of Removal of Concrete Driveway; 8,000 LF of Removal of Concrete Curb and Gutter; 12,000 LF of Sawing Pavement; 19,000 LF of Traffic Stripe (Multi-polymer, 4” Wide); 16,000 LF of Construction Traffic Stripe (Paint, 4” Wide); 10,000 EA of Construction Zone Pavement Markers (Flex Tabs); 1,000 LF of Crack Sealing; 104,920 lbs. of Reinforcing Steel; and 1,715 LF of 5/C Traffic Signal Electrical Cable.