Specifications include, but are not limited to: To date, 22 new poles for the line replacement work have been set next to the existing line, and the existing transmission and distribution lines have been transferred over to another 13 new poles. Under this contract, new cable and pole top equipment are to be installed on all 35 poles, pursuant to the design drawings included in this IFB. In addition, the existing distribution cable is to be transferred over to the 22 new poles set next to existing. Interested Bidders are to provide labor, equipment and any other subcontractors required for all work as specified herein. Pole line hardware, as detailed in the attached list, will be supplied by HG&E. It is the responsibility of the Contractor to provide any additional materials not included in the attached list that are deemed necessary for the job based on the review of design drawings