Specifications include, but are not limited to: The City of Silverton is seeking bids to complete an asphalt pavement grind and overlay project on multiple City owned roadways. Two roadways are currently asphalt (Silver Loop, High Streets). These 2 roadways will have the project scope of 2” grind and inlay full width of roadway. Silver Loop St is 1130 feet long, while High St is 544 feet long. There will be 2 ADA ramps that will need to be installed with some additional curbline work. Adams St is currently concrete surfaced and will require multiple locations of concrete removal with roadway base installation in these locations per PWSD. Adams St will require a leveling lift with a 2” overlay. Adams St will require the contractor to excavate 10 feet on each end of the concrete roadways so the overlay pavement can blend in with the existing.