The demo of the two existing generators and UST systems and replacing with two new 2 megawatt generators with single 30,000 gallon UST performed in two phases. Phase 1 being removal of the two existing UST systems and installing the new UST system. The new system shall be temporarily plumbed to service the existing generators during anticipated extended lead times of the new generators. Awarded contactor must provide temporary fuel storage to maintain 100% uptime to SRCI. Phase 2 will be the demo of existing generators and installation of all new electrical equipment; generators, paralleling controls, docking stations, load banks, and all required connections and interconnects. Connecting the new generators to the new fuel storage system while providing temporary generator and accessories to maintain 100% uptime to SRCI.