Specifications include, but are not limited to: • Contractor will excavate the ditch line listed in this contract to restore adequate flow. o Dredge existing ditch line to remove all vegetation, sediment, trees, and any other material or items that are impeding the flow. o Uncover sections of ditch line that are overgrown with vegetation and trees. • Contractor is to implement best management practices for storm water runoff for the duration of the project. • Spoils can be placed along ditch side as long they don’t impede intended flow. • A contingency quantity of 4x8 rip rap, placed, has been included for any area after restoration that it may need erosion control. • Construction easement for this project have been secured by the city. • Any damage or disturbed areas required for ingress/egress shall be returned to prior conditions.