Specifications include, but are not limited to: 1. They expect to install approximately 2 million feet of fiber optic cabling to serve the City of Greenville and surrounding areas. Approximately 1 million feet will be attached to GUC poles and another 1 million feet will be installed underground. 2. They plan to average 100,000 feet of cable installed per week split between OH and UG for main trunk lines. 3. The cables will utilize GUC poles, public street rights of way, and mainly install where existing cable tv and telephone lines are located. 4. They anticipate mobilizing approximately 20 underground contract crews and 7 overhead contract crews. 5. The plans for the network will be completed in twenty four months and beginning in June 2024. 6. Service drops to homes would be installed later by different crews at the time of a service request by a new customer. 7. The service area will be the City of Greenville. 8. Construction expected to start in June 2024 with service available to first customers about four months later. 9. Major construction will be completed within an twenty four month timeframe.