A. Contractorshall haul and place Hot Mix Asphaltfor Morrow County Public Works on Toms Camp between Kunze and the canal, and Root Ln between Wilson and Rippee. Paved surface shall be a 1” compacted average pre-level and a 2” compacted overlay. Paved width shall be 21’. Root Ln is estimated at 5200 linear feet. Toms Camp is estimated at 2755 linear feet. B. Contractor shall use Hot Mix Asphalt as described below. a. ½” ACP Level 3 Hot Mix b. ½” ACP Level 3 Hot Mix shall meet Oregon Department of Transportation (ODOT) Specifications, section 00744 C. Morrow County estimates quantities of Hot Mix Asphalt at 3,300 tons. D. Contractor will provide traffic control as described in the Oregon temporary traffic control handbook. E. Morrow County designates 8th Street Pit in Irrigon for dumping of any grubbing materials or any materials needing removed during the sub-base and paving phases of the project. Contractor is responsible for loading and transport of all materials. F. Contractor will supply crushed aggregate for the Sub-base phase of the project if needed. G. Contractor will supply and place Temporary Pavement Markers at centerline following paving of the second lift at a span of 40ft. H. Morrow County will place shoulder rock following completion of the paving phase. I. Morrow County will supply and apply permanent pavement markings and striping.