The work includes but is not limited to: Installing new storm system of approximately 4,300 linear feet of 8-inch, 12-inch, and 18-inch diameter storm sewer pipe, including 59 Type 1 and Type 2 catch basins. Improving 3 private property stormwater drainage ditches. Installing new water system of approximately 7,000 linear feet of 8-inch diameter class 52 cement- lined restrained- joint ductile iron water pipe with polywrap, restrained- joint fittings, gate valves, fire hydrant assemblies, and thrust blocking. Installing ( 136) 1-inch, (1) 1.5-inch, and (1) 2-inch water service connections and transfer of domestic water services. Testing, poly- pigging, disinfecting, and flushing of water mains. Trench excavation, including removal of existing unsuitable material, disposal of excavated material, shoring, and dewatering. Trench backfill with suitable material and compaction to required standards. Removal and replacement of asphalt concrete pavement, asphalt grinding and HMA overlay. Protecting of existing utilities, utility potholing and resolution of utility conflicts. Construction surveying, staking, and production of as-built drawings. Temporary traffic control measures in accordance with the contract documents and applicable City of Renton and MUTCD standards. Installing and maintaining adequate Temporary Erosion and Sediment Control measures and restoring all disturbed areas.