Specifications include, but are not limited to: • Install a minimum 45kW liquid cooled, 120/240 volt single phase , liquified propane gas fueled generator with a minimum 200amp service entrance (SE) rated automatic transfer switch (ATS) • Construct and pour a concrete pad for the generator field located near the fire station • Install ATS near the electrical meter and reroute service entrance cable through ATS • Trench & install raceway, power and control circuit cabling from the ATS to the generator • Provide electrical material and labor to complete the installation • Provide activation, start up, testing and end user training • Coordinate with Pickens County Building maintenance personnel for location of new LPG tank for fuel supply for generator. o Required tank mounting/ securing and tank to be provided by Pickens County & County selected vendor • Provide needed gas piping and connections from LPG fuel tank to generator