Specifications include, but are not limited to: A. Project 1-Elk Street bridge 1. Labor and materials to install approximately 677' of four inch galvanized conduit on the side of the Elk Street bridge over the train yard, located between Smith Street and Lee Street, in the City Of Buffalo, NY, per the attached engineering drawings. 2. Labor and materials to install two 24" X 36" handholes at each end of the conduit build. 3. A pull rope will be placed in the conduit from handhold to handhole by the contractor. 4. It is anticipated that construction will be done in Q2, 2024, pending the obtaining of permits from the various railroad companies and the City of Buffalo. All permits will be obtained by ErieNet, and hard copies must be onsite at all times. 5. The scheduling and cost of traffic control is the responsibility of the contractor. 6. The scheduling of any required railroad flaggers is the responsibility of the contractor. The cost of railroad flaggers is the responsibility of the contractor and is billable to ErieNet at cost +10%. B. Project 2-Niagara Street bridge 1. Labor and materials to install approximately 75' of four inch galvanized conduit on the side of the Niagara Street bridge over the Scajaquada Creek, located between north of Forest Ave, in the City Of Buffalo, NY, per the attached engineering drawings. 2. Labor and materials to install two 24" X 36" handholes at each end of the conduit build. 3. A pull rope will be placed in the conduit from handhold to handhole by the contractor. 4. It is anticipated that construction will be done in Q2, 2024, pending the obtaining of permits from the the City of Buffalo. All permits will be obtained by ErieNet, and hard copies must be on-site at all times. 5. The scheduling and cost of traffic control is the responsibility of the contractor.