Specifications include, but are not limited to: Project CP1229LS04 SE Lift Station: • Determine the location of the lift station on the SEWRP site and the appropriate size and types of pumps. • Evaluate the piping needed for bypass and the need for odor control for the new lift station. Project CP1229FM01 Southeast Lift Station Force Main: • Determine alignment for the new force/gravity main. Three alternative alignments are required. • Determine the size, slope, and material of the gravity sewer line if needed. • Coordination of the hydraulics between the lift station and the force main scopes. Project SEWRP Facility Closure: • Update 2018 Mater Plan for SEWRP and GWRP. • Identify what equipment will be removed from the facility. • Perform a safety assessment for remaining structures and equipment to ensure safe decommissioning.