Specifications include, but are not limited to: This project consists of removal and replacement of the failing concrete alley approach on the east side of SW Jackson between SW 8th Street & SW 9th Street. See image 1 on page 3 of this document. The redline indicates sawcuts and limits of removal and placement of new concrete. All existing utility lids shall be matched in place. Aggregate Base shall be placed 6” thick below the 8” Non-Reinforced Concrete Pavement. The table below provides the bid items and quantities included with this project. Subsequent sections provide additional information regarding these bid items. 1 Mobilization 1 LS; 2 Pavement Removal 33 SY; 3 Unclassified Excavation 10 CY; 4 8” Non-Reinforced Concrete Pavement 33 SY; 5 Combined Curb & Gutter, Type I 30 LF; 6 Aggregate Base - Type AB-3 12 TONS; 7 Traffic Control 1 LS...