- Replacement of a bent ladder support angle in Section 9-bay 3. - Replacement of loose leg pad bolts in sections 11, 21, 37, 42, 49, 51, 52, and 59. - Replacement of the loose diagonal member connection bolts in sections 24, 26, 28, 29, 30 and 58. - Replace the guy wire dampeners on all legs of the top 3 guy wires. - Tighten all “jam” nuts on anchor to guy wire connections - Relocate Snubber cables to a location that removes them from the earth and secures them. - Primer and clean/coat areas of rust with zinc rich primer at each anchor point. - All necessary materials needed to make such repairs including the appropriate dampeners for the top 3 guy wires on KMOS’ 2000’ foot Rohn tower. - Mobilization, transportation, and lodging for the tower crew. - All freight and material transportation costs. - All manuals or required training for newly installed equipment. - Copies of any engineering documents created for the project.