Specifications include, but are not limited to: A. The purpose of this specification is to pre-purchase air handling units. The rigging of the equipment and accessories to their final location, installations, connections, and power and controls, will be provided by the installing contractor. B. In addition to furnishing the air handling units, the vendor shall include the following items on its bid pricing: 1. Shipping and handling costs FOB site. 2. Knock-down “build in place” construction assembly. 3. AHU inspection C. The following items shall not be part of this pre-purchase bid, but shall be included in Phase 1 of the library project: 1. Inspection and adjustment of fan assemblies. 2. Start-up service and Owner training 3. Field performance verification