Specifications include, but are not limited to: 1. Installation • Furnish, install, operate, and maintain up to 21 sewer flow meters and install them in locations selected by Pierce County Sewer Division across the County. • Coordinate removal of the existing flow meters. It is anticipated that the existing flow meters will be removed by the current contractor in early January. • 18 flow meters shall be installed at the locations shown in Exhibit A Map and As-Built Drawings, unless otherwise instructed by the County. • This includes providing all traffic control and confined space entry personnel and equipment, hand tools, personal protective equipment, safety gear, and manhole entry equipment necessary for installation. • The Contractor shall have the ability to furnish, install, operate, and maintain up to 3 additional flow meters at 3 or more additional locations within the Pierce County Sewer Service Area, if requested, by the Sewer Division during the duration of the contract. • Provide an installation schedule and installation details at each of the 18 flow meter locations. Installation is projected to begin on July 1, 2024, and must be complete by July 31, 2024, with all flow meters operational. • Provide procedures, schedule, and documentation for meter calibration. • Provide procedures for installation and provide documentation of installation (pictures, diagrams, etc.). • Provide equipment that has an internal power source. • Provide sensors that are able to accurately measure gravity flow in pipes with diameters ranging from 8" to 84". • Sensors must measure the depth, velocity and flow (minimum, maximum and average) with the following levels of accuracy: Depth accuracy of +/- 0.2 inches (maximum) Velocity accuracy of +/- 0.3 feet per second (maximum) • Provide intrinsically safe equipment that communicates via a wireless network for the duration of the contract. • Provide installation pricing for each flow meter at the existing locations and for the 3 or more additional flow meters (21 flow meters total). 2. Data Collection and Reporting • Provide raw flow data at 5-minute intervals, uploaded at a minimum once daily, and available on a secure website accessible to the County personnel at all times. • The Contractor must provide a plan to verify the quality of the data on a quarterly basis and make the data available for download in a .csv file or Microsoft Excel compatible file type on the website. • The Contractor must provide proposed equipment specifications and a statement explaining and guaranteeing the collection of valid data points. Describe the approach to quality assurance, anticipated up-time, and eliminating invalid data. Provide a cost reduction or owner credit strategy when the stated up-time and data quality is not met (e.g. discount proportional to the actual, valid data points reported divided by the total number of expected valid data points per quarter.)...