CONTRACTOR shall provide and install 100 linear feet of 50’ tall netting as indicated and shown on Sheet C2 attached with these documents. The scope includes installation of three (3) new wooden support poles, as indicated on drawings, to support new netting system. New hardware, cable and netting, as specified below, shall be installed upon new wooden support poles. A pre-project site meeting shall be required prior to commencement of construction activities to coordinate the final location of new netting system and to coordinate entry and exit to project site. Exact quantity and size of new netting to be confirmed by CONTRACTOR. Reasonable care shall be taken to mitigate damages to existing surfaces during construction activities.