Specifications include, but are not limited to: Construction of 4-inch water transmission main, and 2-inch diameter electrical conduits with power conductors and water level transducer cable, from new municipal Wells 28 and 29 to the City of Abbotsford Eau Pleine Water Treatment Plant. Water main and electrical conduit shall be constructed by horizontal directional drilling methods below wetlands. The work also includes construction of a 10’ x 12’ prefabricated FRP Metering Building adjacent to the Water Treatment Plant; process piping within the Metering Building, and motor control center and SCADA system modifications at the Water Treatment Plant. The work also includes construction of gravel access driveways, grading, and turf restoration. It is the intention of the Owner to award the project to a single General Contractor. The anticipated substantial completion date is September 30, 2024 and final completion date is October 31, 2024.