Work to include the following: All required safety equipment to complete the work. Cleaning and TV inspection of sanitary sewer pipelines, Pipeline Assessment and Certification Program (PACP) Certification. Installation of 21-inch CIPP liner per ASTM F1216. Pre & post CCTV inspection captured digitally and supplied via link or OSB drive to the City of Danbury. By-pass pumping for pipes to be relined up to 4” pump and soft discharge hose from manhole upstream and discharge in manhole downstream from manhole being worked in (approximately 800 feet). Re-opening of lateral connections. Traffic control to consist of simple signs and cones necessary for the protection and maintenance of traffic and pedestrians. Dispose of any debris removed from sewers during the cleaning operation at a City of Danbury Public Works Complex, 53 Newtown Road.