Specifications include, but are not limited to: Project is being issued in multiple bid packages. 1. Demolition Bid Package (Issued 15 May 2023): Demolition of the existing elementary school and the site work per the delineation line on the Site Drawings. 2. Bid Package 2 (Issued 10 August 2023): Footings and Foundations: Underground utilities and foundation work and concrete. 3. Bid Package 3 (Issued 11 September 2023): Structural Steel; 4. Bid Package 4 (Issued 15 September 2023): Electrical Switchgear; 5. Bid Package 5 (Issued herewith): General Construction. 3. Bidding for phases shall be separated & clearly identified in the bid submission. 1. Base Bid: Provisions for future photovoltaic collector system including the on-line monitoring system, the electrical distribution system and branch circuit conduits for approximately twelve (12) future inverters stubbed to the roof and capped for future installation at locations to be determined by the electrical engineer. Base bid shall also include provisions in roofing warranty to allow installation of system without voiding or affecting Owner's warranty rights. 2. Alternate: Provide the cost for the rooftop photovoltaic system as indicated on the Drawings and as specified in Section 26 3100,"Turnkey Rooftop Photovoltaic Collectors". The cost shall also include the slip sheets at roofing.