Specifications include, but are not limited to: • McCall Dining- Demolition-Remove boiler closest to the double doors. • Install new Seller’s steam boiler. 125 horse powered boiler 3 to 1 turn down. Sized by Louisiana Steam. • Install boiler feed and pump systems. Sized by Louisiana steam. The new boiler system will require shutdowns to make tie ins for the new system. The new boiler will work in concert with the old boiler. • The new boiler system will have Bacnet controls added for integration into the building automation system. Building control systems will be by others. • All connections and flues will be installed by contractor. The flue system extending above the roof line shall be a new pipe, collar, and cap. All new flue systems. • Replace all condensate piping in the mechanical room. • All piping extending outside of mechanical rooms will be extended to ground level to ensure that when boiler is blow down to remove condensable it will now scald people walking the area. • All piping will have two-inch fiberglass insulation. Flow arrows will be installed, and piping marked. • All boilers will have a gas kill switch installed at the doors exiting the mechanical room doors per fire marshal. • All construction debris will be cleaned up daily. • Any electrical hookups will be part of the mechanical contractor’s contract. • All boilers will have bac-net hookups for controls. • Davis Bacon ACT wage guidelines will be followed. • All welded modifications to the gas pipe will be done by a certified welder. Paperwork will be handed over to the Physical Plant director to be delivered to department of natural resources. • All shutdowns will be approved by the VP and Physical Plant Director. • All equipment will be energy efficient and meet the Entergy solutions criteria for rebates.