Specifications include, but are not limited to: scope of Work: Relay: Mount the new SEL 700G in the Unit 1 console area located in the control room. Re-route all the old wiring from the existing Basler GSP100 relay located in the back of the control room. Re-wire all permissive inputs that are presently in series with the close control switch to be inputs to the 700 G as shown on the prints. Extensive field verification is required since many of the inputs and outputs are not shown on prints or labelled. Affix destination labels to all wires that are added or modified. Mark redlines on the supplied drawings to show wire designations and colors if applicable Test the following relay elements: 51P, 51N, 151N, 46, 24, 25, 27, 59, 81. Verify permissive elements show closed when ready and allow relay to issue a close command. All wiring shall be a minimum of #12 stranded SIS except for CT circuits which shall be #10 stranded SIS.