Specifications include, but are not limited to: CONCRETE • Remove existing artificial turf and subgrade from 2 separate tee boxes o Work to be done on one tee line at a time, so the other is accessible for daily use o Work on second tee line cannot commence until first tee line has cured and appropriate hitting mats have been installed by Golf Management • Re-level, pack and prep with suitable subgrade material • Install 2” thick wood forms • Pour 3000psi concrete to a depth of 4 inches o Based on location, it should not require pump truck, only wheelbarrow or Georgia Buggy • Final surface finished with a steel trowel or hand float and brushed with a lightweight brush in a transverse direction producing a uniform gritty surface • All edges rounded to ¼ inch • Expansion joints cut to depth of 1 inch • After concrete has cured, forms to be removed and the outer edges backfilled with suitable earth, uniformly spread and lightly compacted • Grass sod to be installed on backfilled soil along perimeter of concrete • All excess material and debris to be hauled off and disposed by vendor • After hours work may be available with appropriate lighting and safety measures in place. Will require CNE management and CNE Security approval. Concrete Dimensions • Tee Line 1 (west tee): 93 linear feet x 6 feet wide x 4 inch deep • Tee Line 2 (east tee): 85 linear feet x 6 feet wide x 4 inch deep • Linear feet can be adjusted marginally only by agreement of vendor and golf management