Specifications include, but are not limited to: OR22: Big Cliff Dam – Mongold Slide Section of the North Santiam Highway (Rt. No. OR22) near Detroit. FAP No. S162(061). ($ 5,000,000 - $ 10,000,000). Req. approx. 700 hrs training; 180 ft2 temp. signs; 4 ea PCMS; 2,500 hrs flag.; 2 ea flag. sta. light.; 100 ea TCS; 900 hrs pilot car; 2 ea AFAD; 137,544 ft temp. striping; 2 ea TMA; 15 ton contam. soil disp.; 2 ea soil samp. test.; const. surv. wrk.; 6,400 yd3 exc.; 1,000 yd2 subg. stab.; 1,425 ft barr. Mnt. rk. prot. screen; 1,573 yd2 br. dk. CPPR; 79 yd2 cl. 2 prep.; 128 ft ctrl. jt.; 14,153 ft2 poly. memb.; 12 yd3 gran. str. bkfl.; 1,300 lb reinf.; 6 yd3 str. conc.; 12,615 yd2 CPPR; 1,300 ton aggr. shldr.; 5 ton emuls. asph. fog coat; 43 ton emuls. asph. tack coat; 15,200 ton ACP (938 ton PG 64-28); 2 ea core corr.; 5,000 yd2 ACP rep.; 21,294 ft gd. rl.; 1,800 ft conc. barr.; 6.17 mile rmbl. strips; 139,000 ft paint striping. Completion Time: November 1, 2024. Classes of Work: either A) Asphalt Concrete Paving and Oiling, or B) Miscellaneous Highway Appurtenances. THIS PROJECT CONTAINS ASPHALT AND FUEL ESCALATION CLAUSES. THIS PROJECT CONTAINS A 11% DBE GOAL. PROJECT MANAGER: SCOTT NELSON, EMAIL: SCOTT.NELSON@ODOT.OREGON.GOV