Specifications include, but are not limited to: 1. Mobilization/Demobilization LS 1 2. SWPPP (or NOI, Use Site's current SWPPP) LS 1 3. Contractor's Surveyor LS 1 4. Dust Control LS 1 5. Geosynthetic Clay Liner (GCL) Storage Pad LS 1 6. Mass Excavation CY 438,000 7. Fine Grading and Compaction of Subgrade SF 566,280 8. Cell 6 Composite Liner Tie-in to Cell 4 LF 1,162 9. Cell 6 Composite Liner Tie-in to Cell 5 LF 479 10. Purchase and Install Geosynthetic Clay Liner SF 592,700 11. Purchase and Install 60-mil HDPE Textured Liner (2-sided) SF 159,561 12. Purchase and Install 60-mil Smooth HDPE Liner SF 433,139 13. Purchase and Install 8 oz Geotextile SF 15,500 14. Excavate, Backfill, and Compact Liner Anchor Trench LF 479 15. Purchase and Install Plywood in Transition Zones LF 1,162 16. Construct Liner Protection Berm along Edges of Completed Liner CY 2,600 17. Haul and Place On-Site Protective Soil Layer Material CY 45,500 18. Purchase and Install 6" HDPE SDR 11 Perforated and Solid-Wall Leachate Pipe LF 1175 19. Purchase and Install Leachate Trench Coarse Aggregate CY 120 20. Purchase and Install Bollards LS 1 21. Purchase and Install Edge of Liner Markers LS 1