Specifications include, but are not limited to: A. The work includes the furnishing of all labor, materials, equipment, services and incidentals for the “Pembroke Pines Water Utilities –Holly Lake and Academic Village ATS Replacement” project. B. The project consists of, but is not limited to two (2) automatic transfer switches (ATS’s) replacement. C. The temporary power shall include temporary generators, temporary conduits and temporary conductors as per specifications and plans; WORK SEQUENCE - A. Incorporate sequence of the Work into the Progress Schedule. B. Demolition of existing ATS. C. Set up the temporary sound attenuated generator. D. Install new ATS. E. Restore all work areas and test, start-up and train personnel on new system modifications.